Second report lays into Ministry of Defence over sub defueling and dismantling

by | 3rd July 2019 | News

Home News Second report lays into Ministry of Defence over sub defueling and dismantling

Warship Technology: Jul/Aug 2019Submarine

The Public Accounts Committee (PAC) in the UK published a report on submarine defueling and dismantling on 15 June 2019 that was highly critical of the Ministry of Defence.

 

Publication of the report followed hard on the heels of another report on the subject published by the National Audit Office (NAO) in April 2019 that issued a stinging appraisal of efforts to dispose of the UK Royal Navy’s nuclear-powered submarines (see Warship Technology May 2019).

 

The PAC report found that the Ministry of Defence’s failure to dispose of retired nuclear submarines “is unacceptable and unnecessary” and said further delays to submarine disposal are possible as the first submarine dismantling will be three years late.

 

The PAC report also highlighted the fact that by the mid-2020s, the Ministry of Defence is likely to find itself without any further storage space for decommissioned nuclear submarines.

 

The PAC said progress disposing of retired submarines “has been a serious disappointment” and the project to do “has moved at a glacial pace.”

 

The PAC said a 15-year delay had led to extortionate storage and maintenance costs which are now costing the taxpayer £30 million per year and that, as more submarines are retired from service, the Ministry of Defence seems increasingly likely to find itself without any further storage space by the mid-2020s.

 

“The Ministry of Defence is rapidly approaching crisis point and simply cannot afford any further delays, particularly as much of the money currently being spent on the project is not going directly towards either defueling or dismantling,” the report said.

 

“It is clear that the commitment to dismantle its first submarine – Swiftsure – by 2023 will not be met and will likely be completed three years after the target date.

 

“The scale of the task faced by appears even more challenging given the defence affordability ‘black hole’ which totals at least £7 billion.”

Related Posts

News from the ACT Section May 2024

Technical Presentation –– 30 April 2024 John Polglaze, Director of PGM Environment, gave a presentation on Warship Environment Protection: Avoiding Utopian Aspiration in Favour of Rational, Balanced, Objective Pursuit to a meeting at UNSW Canberra at ADFA, with the...

News From The NSW Section May 2024

Technical Presentation –– 1 May 2024 Jonathan Branch, Principal Consultant and Director, Invicta Maritime Solutions, presentation on Pollution Prevention in a Defence Context: Could an International Naval Ship Pollution Prevention Code be Feasible? to a joint meeting...

Solar Boat Challenge — 25 November 2023

Solar Boat Challenge — 25 November 2023

RINA Tasmanian Section supported the annual Schools Solar Boat Challenge, held on Saturday 25 November 2023 at Clarence High School. Unfortunately, it rained on the day; however, enough UV light penetrated to ensure that all vessels performed well. Chris Davies spoke...

Tasmanian Section Christmas Party — 1 December 2023

Tasmanian Section Christmas Party — 1 December 2023

The Tasmanian Section Christmas party was held at the Penny Royal Wine Bar and Restaurant in Launceston on the evening of Friday 1 December 2023. There is a replica of the brigantine Tamar which ‘floats’ on rails alongside but, unfortunately, attendees were not...

You need to login to contact with the Listing Owner. Click Here to log in.